The Job Schedule by Cost Code report, included with Signature 2018 R4, requires manual deployment and location path setup on each user's computer accessing Schedule.
Deploy the Report
-
Launch Microsoft Dynamics GP and then go to Microsoft Dynamics GP > Tools > Setup > Service Management > Module Setup > Service Options.
-
Under Reporting at the bottom of the window, select Run Wizard and then select Continue.
-
Select Next.
-
Complete the server information and select Next.
-
Select the System Database and then select Next.
-
Verify the information and select Next.
-
In the next window, unmark all checked boxes.
-
Expand Job Cost. by choosing the +.
-
Mark the checkbox next to Job Schedule by Cost Code and select Deploy.
-
After the report has been deployed, you are returned to the Report Wizard window. Select Cancel to close the window. Repeat this for any additional company databases.
Set Location Path
-
Launch and connect to the SQL Server.
-
Run the following SQL statement to update the Job Schedule by Cost Code ReportLocation, replacing the Report URL with your actual report URL.
UPDATE WSRepts SET ReportLocation = 'Report URL' WHERE ReportReference = 'Job Schedule by Cost Code'